Create and Work with Checkpoints
As you are working with interfaces and reports, you may want to create checkpoints to refer back to at a future time. Following are the permissions needed for creating and working with checkpoints:
Checkpoint Roles
| Role | Permissions |
|---|---|
| Administrator | - Create checkpoints that display for all users and can be included in comparisons. - Rename checkpoints. - Delete checkpoints. |
| All users | Create checkpoints that are viewable, and able to be included in comparisons, only by the user who created it. |
See also Approve a Plan.
To create a checkpoint
- In a pivot table interface, on the menu (
), click Save Checkpoint. - In the Save As screen, in the File name field, type a name for the checkpoint.
An official checkpoint (or approved plan) uses the following naming convention:
Final YYYY-MM
For example, the official checkpoint for February 2013 is Final 2013-02. Official checkpoints are used in the Triangle and Current Year reports.
See Work with Triangle Interfaces. 3. On the Share Type list, select one of the following:
- Private: Other users are not able to see the checkpoint.
- Public: Other users are able to see and work with the checkpoint.
- Click Save.
To open a checkpoint
- On the menu (
), click Open Checkpoint. - In the Open screen, select a checkpoint and click Open.
A note displays below the dynamic report that says Checkpoint: followed by the name of the checkpoint you opened. If you do not see this, you did not successfully open the checkpoint.
3. To clear the checkpoint, on the menu (
), click Clear Checkpoint.
To rename or delete a checkpoint
-
On the menu (
), select one of the following: -
Save Checkpoint
- Open Checkpoint
- In the Save As or Open screen, select a checkpoint and do one of the following:
| To rename the checkpoint | 1. Click Rename. 2. In the File name field, type the new name and click OK. |
| To delete the checkpoint | 1. Click Delete. 2. Verify you want to delete the checkpoint by clicking Yes. |